Submarine cable in Baku (AZ)

Facts

Status

Completed

When?

Aug-Nov 2012

Where?

Baku Oily Rocks

This project consisted of the following elements:

  • To prepare drawings for the cable cage to Baltiskiy 106 vessel.
  • To manufacture the cable cage and transport it to the vessel and install it.
  • To plan the loading of the marine cable with mobile crane and barges.
  • To transport the cable loading equipment by sea to the loadinplace.
  • To pilot the vessel and moor it offshore at the cable loading site at Båtviken in Kantvik
  • To load the 21 km long marine 35kV cable into the vessel at Prysmiann premises.
  • To prepare drawings for the cable arch to enable the transfer of the cable from Baltiskiy 106 to the cable loading barge.
  • To travel to Baku in Azerbaijan and supervise the discharging of the cable form Baltiskiy 106 to the cable laying barge.
  • To supervise the installation of the cable laying machinery on the cable laying barge in Baku
  • To supervise the cable laying for Prysmian and Nobel Oil account on the Oil Rocks oil field.

 